Maintenance Plan – VN/93

The routine maintenance schedule has to be followed as described below. Valid for gas operation with TPS turbo charger, stationary power plant application and marine engines. NOTE: All maintenance steps should be performed while engine is stopped!

Procedure/Interval:

What to do:

Procedure 1 / Every 3 months

 

  • Check the negative pressure with u-tube manometer or digital manometer. Adjust if necessary! Setting level is 60,00 mmH2O!
  • Replace the sintered bronze air filter/fresh air filter (Part no.: 10042) in the measuring head.
  • Clean the fresh air bores in the measuring head. Use the cleaning needle (Part no.: 10135).
  • Clean both infrared sensor glasses in the measuring head with cotton pins and technical alcohol.
  • Perform functional test with test glass kit.

                                   For step-by-step guide, see the dropdown boxes below.

Procedure 2 / Every 6 months

 

  • Replace filter in pressure regulator (Part no.: 100170).

If you have a water separator:

  • Replace filter cartridge of water separator

                                   For step-by-step guide, see the dropdown boxes below.

Procedure 3  / Yearly

 

  • Replace maintenance kit for base plate (100153, 100154 or 100155).  Clean the inside & outside of base plate.
  • Check performance of pressure regulator- replace parts if necessary!
  • Clean suction pipes/ pipe system and siphon blocks with compressed air!
  • Check scavenging air outlet behind the control cover manually (low-right) by feeling the air stream.

                                   For step-by-step guide, see the dropdown boxes below.

Procedure 4 / Every 2 years

 

This procedure is to be carried out by authorized service personnel!

  • Overhaul the complete oil mist detector system. 
  • Replace maintenance kit for base plate (100153, 100154 or 100155).  Clean the inside & outside of base plate.
  • Check performance of pressure regulator- replace parts if necessary!
  • Clean suction pipes/ pipe system and siphon blocks with compressed air!
  • Perform functional test of entire oil mist detector system with smoke generator (Part no.: 10353 & 10097) or smoke test (Part no.: 151780).

                                   For step-by-step guide, see the dropdown boxes below.

Procedure 4 / Every 4 years

 

  • Replace complete oil mist detector or measuring head with an exchange unit. NOTE: When ordering an exchange unit – always inform us about engine type!
  • Replace maintenance kit for base plate (100153, 100154 or 100155). Clean the inside & outside of base plate.
  • Check performance of pressure regulator- replace parts if necessary!
  • Clean suction pipes/ pipe system and siphon blocks with compressed air!

If you are ordering a complete exchange oil mist detector unit, there is no need to replace maintenance kit for base plate.

                                   For step-by-step guide, see the dropdown boxes below.

Your professional partner within Oil Mist Detector technology. Engine Protection Partner AS is Schaller Automations authorized repair, sales and service centre based in Scandinavia. Headquarter for Norway, Svalbard, Jan Mayen, Faroe Islands, Aaland Islands, Sweden, Finland, Denmark, Iceland, Estonia, Latvia, Lithuania and Greenland. We are represented world-wide! Main training center for clients such engine manufactorers, the norwegian military, scandinavian maritime schools, hundreds of ship owners and more.

Our Certification Partner

EPP AS © Copyright 2020.

A part of Engine Protection Partner Group

© The information and media under this domain (www.epp.no) is the property of Engine Protection Partner AS (Reg. no.: 976 683 560) and may not be copied or used for any purpose other than for which it is supplied without the express written consent of Engine Protection Partner AS. If any of the aforementioned elements are copied without our written consent, this will lead to legal action from our side!